Protective Structures

BRM Blast-Resistant Modules

40-foot modules for offices, control rooms and technical facilities at industrial sites.

Exterior of a 40-foot Alfa BRM module
Module exterior (configuration example). Final configuration is defined during design.

Module Specifications

Format40-foot blast-resistant module (BRM)
Dimensions, L x W x H12,192 x 3,658 x 2,896 mm
Approximate mass24,000 kg; subject to equipment configuration
ConstructionMultilayer steel structure with fire-protection materials
EntranceDouble-leaf door at the end
ApplicationOffice, control room or technical module

Protection Parameters

The initial proposal specifies an overpressure of 10 PSI (68.95 kPa) and EI 120 fire resistance. The source materials reference GOST R 57471-2017 with amendment 2 and GOST R 53307.

Blast pressure, duration and impulse, installation conditions and envelope configuration are agreed in the project specification. Performance confirmation and certificate applicability depend on the agreed configuration; a presentation does not replace a test report.

Building Services

  • Air conditioning with redundancy.
  • Distribution board and internal wiring.
  • Fire alarm.
  • Ventilation and pressurisation.
  • Gas detection.
  • Lighting and socket outlets.

Equipment and external connection requirements depend on room use and operating conditions.

Example BRM interior layout
Interior example. Desks, cabinets and partitions are optional and are not included in the base supply.

Layout for Your Facility

The module can serve as a control room, office or technical unit. Workstations, cabinets and partitions are agreed separately. Specify its intended use, occupancy, design blast load, building services and installation site.

Dimensions, Usable Area and Layout

The external footprint is approximately 44.6 square metres: 12.192 x 3.658 m. This is not the usable floor area: wall thickness, interior finishes and service zones reduce it. Clear height, aisle widths, occupancy and equipment sizes are determined by the working layout.

Defining the Blast Load

A single PSI value is insufficient for an engineering comparison. Specify peak pressure, positive-phase duration, impulse, load shape and allowable damage. Distinguish free-field pressure from reflected pressure on a wall. The module's orientation relative to the blast source also forms part of the design basis.

ParameterRequired Definition
Peak overpressurekPa or PSI; free-field or reflected pressure; loaded faces.
Positive-phase duration t+Duration in milliseconds.
Impulse I+Pressure integrated over time, in kPa.s or Pa.s.
Structural responsePermitted deformation, damage and post-event usability.
InstallationSupports, anchors, foundations and design load directions.

RedGuard describes separate tested configurations: an anchored 12 x 40 ft module at 10 PSI / 200 ms and an unanchored module of the same format at 8 PSI / 200 ms. These are individual configurations, not a universal anchoring correction factor. RedGuard test description.

A 200 ms duration and response levels of overseas products are not automatically claimed for the Alfa BRM. These must be agreed and confirmed for the selected configuration.

Frame, Envelope and Protected Openings

Container Reinforcement Structure

The assembly drawing shows the structural frame and the position of the envelope panels:

  • Longitudinal members and transverse floor members forming the base.
  • Vertical wall members connected to the upper frame.
  • Roof crossmembers and the frame around the end door opening.
  • Wall, roof and floor panels shown separately from the frame.

Member sections, material thicknesses, connection details and fixing arrangements are defined by calculations and working drawings for the specified loads. This illustration shows the assembly concept, not a dimensioned fabrication drawing.

The module is a complete system: load-bearing frame, walls, roof, floor, doors, equipment restraints and service penetrations. A reinforced wall cannot compensate for an inadequately designed door or unprotected ventilation opening. This integrated approach is also described by MagOffshore.

  • Doors: agree opening direction, clear opening, locks, seals, closers and emergency escape.
  • Windows: specify performance of the complete assembly, including frame and fixings.
  • Penetrations: coordinate cable and pipe entries with fire resistance, airtightness and blast loading requirements.
  • Interior equipment: specify restraints for cabinets, lights and suspended items.

Configuration options include reinforced doors with panic bars, reinforced hinges and closers, and emergency lighting. These are specification options, not the standard Alfa supply.

Climate Control, Pressurisation and Gas Detection

Air conditioning controls temperature, ventilation provides air exchange, and pressurisation controls the pressure difference between indoors and outdoors. Their operating logic must be coordinated.

SystemDesign Inputs and Decisions
Heating and coolingOutdoor design temperatures, equipment heat gains, occupancy and redundancy.
Ventilation and pressurisationOperating modes, differential-pressure monitoring, airtightness, damper states and power-loss response.
Gas detectionTarget substances, sensor positions, alarm thresholds and integration with site controls.
Power supplyVoltage, phases, available capacity, earthing and backup for agreed loads.
Fire systems and communicationsDetector types, alarms, emergency lighting, data networks and external signals.

If temporary shelter during a toxic release is required, separately specify occupancy duration, permitted leakage and life-support requirements. Ventilation, air conditioning or gas detection alone does not establish this capability.

Siting, Transport and Foundations

Select the installation location with reference to blast, fire and toxic-release scenarios, occupancy and evacuation routes. API RP 752 and RP 753 address siting risks for permanent and portable buildings at process facilities; they are not universal container blast-resistance certificates. Official API description.

  • Agree supports, foundation loads, anchoring and floor level.
  • Confirm transport mass, centre of gravity, lifting points and lifting plan.
  • For the 3,658 mm width, check route restrictions and oversize transport requirements.
  • Provide access to doors and serviceable equipment; check drainage and external connections.

The lifting plan and lifting accessories for each Alfa BRM are defined in its documentation.

Overseas Products: Published Parameters

The following data concern other manufacturers' products. They are reference information, not evidence of Alfa BRM equivalence or certification. Read them with the test conditions and supporting documents.

Manufacturer / ConfigurationPublished DataOriginal Material
RedGuard, 2020 testAnchored 12 x 40 ft module: 10 PSI / 200 ms. Separate unanchored configuration: 8 PSI / 200 ms.Description and before/after photographs
Hunter, refinery project8 PSI / 200 ms; one-hour fire protection, pressurisation and ATEX Zone 2 exterior equipment.Project and photograph
MagOffshore, 40 ft BRM10 PSI / 200 ms; 12,192 x 2,438 x 2,896 mm; 11-18 tonnes. Design verification to DNV-ST-E272 is stated.Exterior, door and interior gallery
MineARC ChemSAFE, PS-BR-9-12-40-10P10 PSI / 200 ms; approximately 12.20 x 3.65 x 2.75 m; 22.7 tonnes. Other sizes differ.Manufacturer brochure
Mecton, 40 x 12 ft10 PSI / 200 ms; Medium Response; 12.192 x 3.650 x 2.900 m; approximately 25 tonnes.Specification and gallery

Medium Response does not mean no damage. RedGuard describes significant damage and repairs before further use. Post-event operability requirements must be specified separately.

Documentation and Acceptance

Agree the documentation package when specifying the supply:

  • General arrangement, layout, external and clear internal dimensions.
  • Design basis: pressure, duration, impulse, supports and allowable damage.
  • Calculations, applicable test reports and certificate scope.
  • Equipment schedule, wiring diagrams and alarm logic.
  • Lifting, installation, anchoring and utility connection plans.
  • Product passport, operating instructions and agreed factory acceptance programme.

DNV-ST-E272 covers design, manufacture, testing, installation and operation of equipment assemblies. A third-party manufacturer's reference to it does not imply DNV certification of the Alfa module. Official DNV scope.

Questions When Selecting a BRM

Can a standard shipping container be converted?

Container dimensions do not establish blast resistance. Changes to the body, openings and services require engineering justification of the complete assembly for the specified load.

Can products be compared by mass alone?

No. Mass depends on dimensions, structural scheme, envelope and equipment. Compare equal loads, installation conditions and damage criteria.

What fire resistance is provided?

The agreed configuration provides 120 minutes of fire resistance for external structural elements (walls, doors, windows).

What information is needed?

Use and location; occupancy and working pattern; blast-load parameters; fire and gas hazards; climate; power supply; foundations, delivery, communications and building services.

Technical reference based on manufacturer, API and DNV materials reviewed on 23 November 2026. Layout, impulse and services diagrams were created for this page. Original overseas photographs are available through the source links.